Finally Completed on July 11, 2022 Pool Construction From Start to Completion On April 8, 2022 the dig was started and completed the next day.
The excavator entering the backyard.
The excavator leaving the backyard. April 9, 2022, the framing started. On April 14, 2022, the Plumbing
was Completed.
April 21, 2022, setting the rebar for the gunite.
April 22, 2022, applying gunite. On June 16, 2022, the original stone
steps
were removed. June 21, 2022, pouring concrete for
the decking.
June 28, 2022, preparing to apply the pebble sheen plaster. Applying the pebble sheen plaster.
The original pool design created on
December 14, 2021.
[Pool Construction] [Pool Complete] [Koi Pond] [Ducks] [Windmill] [Retaining Wall] [Motorcycles] [Track Day] [Sewer Line]
|